Below Threshold Reprogramming for procurement is limited to the lesser of $20 million or 20%, into or out of a program. Is this statement true or false?

Study for the ACQ 1010 Fundamentals of Systems Acquisition Management Test. Dive into flashcards and multiple-choice questions, complete with hints and detailed explanations. Gear up for a successful exam!

The statement regarding Below Threshold Reprogramming (BTR) for procurement being limited to the lesser of $20 million or 20% is true. BTR allows for adjustments within a program's funding and typically addresses minor reallocations without the need for extensive approval processes. This flexibility encourages efficient fund management, allowing for timely adjustments based on current project needs or changing conditions.

The threshold for BTR is defined to ensure that only minor, non-disruptive changes can be made without more formal oversight. If the changes exceed the defined thresholds, a more rigorous review and approval process is necessary to ensure that such alterations align with the broader goals and authority of the acquisition process.

Understanding the context of BTR is essential, particularly in comparison to other types of funding modifications that might have different thresholds or requirements.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy