In which document does the Program Manager address demilitarization and disposal requirements?

Study for the ACQ 1010 Fundamentals of Systems Acquisition Management Test. Dive into flashcards and multiple-choice questions, complete with hints and detailed explanations. Gear up for a successful exam!

The Product Support Plan (PSS) is the document in which the Program Manager specifically addresses demilitarization and disposal requirements. This plan outlines how the program will ensure that products can be supported throughout their lifecycle, including considerations for end-of-life processes such as demilitarization and environmentally responsible disposal. By addressing these requirements in the PSS, the Program Manager ensures compliance with relevant regulations and standards while also demonstrating a commitment to sustainability and effective resource management.

The other documents serve different purposes within the systems acquisition framework. The Acquisition Strategy Report focuses on the overall approach to acquiring a system, detailing aspects like costs, schedule, and milestones but does not specifically elaborate on disposal. The Capability Development Document outlines the needed capability and associated requirements but doesn’t delve into supporting elements such as disposal. Lastly, the System Engineering Plan provides a roadmap for engineering tasks and strategies related to system development, which may touch on lifecycle considerations but would not comprehensively cover demilitarization and disposal specifics. The PSS stands out as the dedicated document that ensures these critical requirements are thoughtfully integrated into program management practices.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy