Which major appropriations category below is NOT included in the Life cycle Cost estimate?

Study for the ACQ 1010 Fundamentals of Systems Acquisition Management Test. Dive into flashcards and multiple-choice questions, complete with hints and detailed explanations. Gear up for a successful exam!

The major appropriations category that is not included in the life cycle cost estimate is investment.

Life cycle cost estimates encompass various costs associated with the acquisition, operation, maintenance, and eventual disposal of a system over its entire life cycle. This includes operating costs, research and development expenses, and maintenance costs. Each of these categories contributes to understanding the total cost associated with a system from inception to retirement, offering a comprehensive view of the financial commitment involved.

While investment costs are indeed critical in the early stages of system acquisition, they typically refer to the initial capital put forth to procure and develop the system rather than ongoing costs that are captured in life cycle cost estimates. Thus, in the context of life cycle cost analysis, investment as a standalone category does not contribute to this overarching financial overview.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy